Advanced utility work for Main Street Renewal - lane reductions on Main Street planned

As part of advanced utility work for the upcoming Main Street Renewal project, Bell Canada will commence construction work to replace the existing Bell ducts. Read this briefing report for complete details. The work along Main Street will include the following:

  • Removal of surface over the existing duct (concrete sidewalk/asphalt roadway/grass);
  • Breaking of the existing clay duct;
  • Encasement of existing Bell Canada lines with a concrete duct;
  • Reinstatement of hard surface with temporary asphalt.

The work is tentatively planned to begin on November 12, 2014. Completion is anticipated by spring or summer 2015, weather dependent. This work stretches from Greenfield Avenue to the north to the McIlraith Bridge to the south. The location of the Bell services within the Main Street corridor varies between within the roadway to under the sidewalk and cross the roadway in some locations. The work to be completed is largely on the east side but some work will need to be completed on the west side as well as across Main Street.

Lane reductions on Main Street are required to complete this work. The first phase of the work will be north of Clegg Street and the second phase will be south of Clegg Street. The first phase is tentatively planned to begin with the section between Hawthorne Avenue and Greenfield Avenue on November 12th with temporary lane reductions. Permanent lane reductions (one lane in each direction + left turn lanes) are required between Clegg Street and Lees Avenue because the work will be done under winter conditions. The permanent lane reductions are tentatively planned to be set-up with pavement markings and construction barrels on the weekend of November 22nd (weather dependent). The construction barrels will be replaced with pre-cast curbs shortly after because pre-cast curbs are easier to maintain during snow removal. Work between Lees Avenue and Hawthorne Avenue will be completed over the course of several weekends with temporary lane reductions. The second phase (south of Clegg Street) will commence after the first phase is complete (potentially spring 2015).

For further information about this project please contact:

Greely - Contractor representative
Jeff Smye (613-229-0264)

Bell Canada representative
Courtney Coopper, Project Manager
E-Mail: courtney.coopper@bell.ca

For information about the Main Street reconstruction project please contact:

City of Ottawa Representative
Josée Vallée, P. Eng.
Design and Construction Municipal East Branch
E-mail: Josee.Vallee@ottawa.ca
Tel.: (613) 580-2424, Ext. 21805

Construction notice for residents of Elliot Avenue and Rideau River Drive

Beginning the week of November 3, 2014, the City of Ottawa will begin construction work on properties located along Elliot Avenue and Rideau River Drive (in addition to Leanne Street, Phoenix Crescent, Payette Drive, and Granada Drive). This activity will include the rehabilitation of several depressed driveway entrances at the roadway edge.

WHO: The City of Ottawa has hired the Contractor, Ottawa D Squared, to complete the work.

WHY: The purpose of the project is to address concerns related to drainage from the roadway flowing onto depressed driveways.

WHAT: The work consists of the removal of sections of asphalt pavement and the construction of the drainage control features within the private driveways and the right of way of these roadways. As a part of the project, the City of Ottawa will be completing some additional roadway and drainage modifications on several of the streets as identified below.

WHEN: This work is tentatively scheduled to begin the week of November 3, 2014 and should last for approximately 3 weeks on several driveways. The work will resume in the spring, depending on the suitability of the weather for construction during the next month. The construction work will likely be completed during the daytime hours. Local sections of the roadway adjacent to the driveway entrances that are affected may be open to local traffic only, while maintaining acceptable traffic flow.

Accessibility is an important consideration for the City of Ottawa. If you require special accommodation, please see contacts below.

For any emergency outside normal working hours on weekdays and weekends, please call the city at 3-1-1.
For further information about this project, please contact the City’s Project Manager:

City’s Project Manager: Jamie MacDonald, 613-580-2424, ext. 16151, jamie.macdonald@ottawa.ca
City’s Construction Site Inspector: Roxanne Tubb, 613-828-7800, ext. 227
Contractor Site Superintendent: Matthew Iacobucci, Ottawa D Squared Construction Ltd., 613-822-1042

Annual General Meeting on November 11

The annual general meeting of the Old Ottawa East Community Association (OOECA) and Community Activities Group (CAG) will take place on November 11, 2014, at 7pm. The meeting will take place at Church of the Ascension, 253 Echo Drive. Please see the following materials related to the meeting:

A social hour will follow the meeting.

Status update on accessing eastern and western Rideau River pathways - UPDATE on Nov. 6

Both paths are currently closed until the end of October as demolition works at Hurdman Bridge are ongoing. Upcoming work at Hurdman Bridge includes headwall work, which will require an additional two week closure per pathway in November. This work will begin on the west side and then switch to the east side.

Pathway status:

· UPDATE: Eastern pathway – remains closed and is anticipated to reopen as early as the week of November 5.

· Western pathway – remains closed and is anticipated to reopen as early as the week of November 20.

City of Ottawa recruiting citizen members for committees and boards

The City of Ottawa is currently recruiting for citizen members to serve on various committees and boards. To be eligible, you must be a resident of the City of Ottawa and 18 years of age or older (city employees are not eligible).

Several positions are available including:

•Board of Health (5 members)
•Police Services Board (1 member)
•Library Board (*5 to 8 members)
• Committee of Adjustment (15 members)

•Transit Commission (*4 members)
•Built Heritage Sub-Committee (*3 members)
•Licence and Property Standards Committee (5 members)
•Shaw Centre – Board of Directors (*2 members)

•Rideau Valley Conservation Authority (*4 members)
•South Nation Conservation (*2 members)
•Mississippi Valley Conservation Authority (*3 members)
• Mohr’s Landing / Quyon Port Authority (1 member)

•Accessibility Advisory Committee (*9 to 15 members)
•Arts, Heritage and Culture Advisory Committee (*9 to 11 members)
•Community Services Advisory Committee (*9 to 11 members)
•Environmental Stewardship Advisory Committee (*9 to 11 members)
•French Language Services Advisory Committee (*7 to 11 members)

* Subject to the Term of Council Governance review and/or Nominating Committee process.

For more information: Visit http://ottawa.ca or contact Carole Legault at 613-580-2424, ext. 28934, (TTY: 613-580-2401) or by email at committees@ottawa.ca.

An Open House/Information Session will be held on Thursday, November 13, from 6:00 to 8:00 p.m. in the lobby at 100 Constellation Crescent

If you are interested, please fill out an application form or submit a résumé and cover letter indicating the committee or board on which you would like to serve including an outline of how your qualifications, specific skills, interests and background are relevant to this committee/board. To confirm residency, please include your home address. All applications must be submitted by Thursday, November 27, 2014 at 4:30 p.m. to:

Carole Legault, Recruitment Coordinator
City of Ottawa, 110 Laurier Avenue West
Ottawa, ON K1P 1J1
Fax: 613-580-9609
Email: committees@ottawa.ca

Syndicate content